0
Date of project
0
kV
Project

Turn-key project for OST

Project-Design, topographycal service, geological study, civil work/ foundation, supply/installation, tower erection, conductor stringing, OPGW stringing, testing and commissioning were the works for which DOKO was contracted from OST Albania in 2015. This was a project for relocation of 400 KV line Tirane 2 – Elbasan 2.